2010 Bond - Progress Status

Summer 2011 Progress Update

Creekside Elementary School
➢ Install Interactive White Boards in classrooms
➢ Install concrete curbs at visitor entrance drive
➢ Reconstruct, seal coat & re-strip areas of the visitor parking lot
➢ Miscellaneous sidewalk replacement

Lakes Elementary School
➢ Install Interactive White Boards in classrooms
➢ Mechanical system replacement such as boilers, circulation pumps, heating system distribution piping, heat pumps & convection heaters
➢ Install new ceiling & lights in music room
➢ Install new sink base cabinet in specified classrooms
➢ Replace the remaining countertops & sinks not done in previous bond
➢ Reconstruct exterior brick wall on north elevation
➢ Install manual transfer switch and emergency generator outlet
➢ Replace some interior wood doors
➢ Window and glass replacement throughout building
➢ Replace receiving exterior door
➢ Install concrete exit stoops in kindergarten rooms
➢ Replace existing coat hooks with new lockers
➢ Replace gang toilet partitions

Round Elementary School
➢ Install Interactive White Boards in classrooms
➢ Construct additional parking south of the main entrance
➢ Improve drainage to the playfield area

Village Elementary School
➢ Install Interactive White Boards in classrooms
➢ Repave hard surface play area.
➢ Extend sidewalk from Epley Parking to create a safer access to the school
➢ Install new freezer and new double deck for the district central kitchen
➢ Upgrade freshman baseball field, irrigation, reconfigure outfield fencing, replace backstop & reconstruct infield surface

Farms Intermediate School
➢ Install Interactive White Boards in classrooms
➢ Mechanical system replacement such as boilers, circulation pumps, hydronic piping, heat pumps & convection heaters
➢ Install air conditioning in gym
➢ Replace some interior wood doors
➢ Replace existing double stack convection ovens
➢ Install new floor in art room
➢ Reconstruct exterior brick wall on west elevation
➢ Install manual transfer switch and emergency generator outlet
➢ Install sound attenuation panels in cafeteria
➢ Replace main entry & gym exit doors and frames
➢ Resurface folding partition in commons area
➢ Paint new ductwork and walls in gym
➢ Provide new ceiling and lights in kitchen
➢ Replace gang wash sink in art room

Middle School at Ore Creek
➢ Install Interactive White Boards in classrooms
➢ Repave parking lot

High School
➢ Install Interactive White Boards in classrooms

Educational Support Service Center
➢ Install Interactive White Boards in classrooms
➢ Remove lower tennis courts & construct new athletic courts
➢ Reconstruct upper tennis courts

1951 Building
➢ Install occupancy sensors in classrooms
➢ Install manual transfer switch and emergency generator outlet
➢ Upgrade electrical service to building
➢ Replace some exterior doors & frames
➢ Provide air conditioning to the gym/lunchroom
➢ Reconstruct hard surface play area & improve site drainage
➢ Remove existing in-wall lunchroom tables & infill with masonry
➢ Replace classroom sinks and countertops & sink base cabinets


January 2010 - May 2011

Since the passage of the Bond issue in February of 2010 we have designed and installed the following projects:

Creekside Elementary School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Lakes Elementary School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Round Elementary School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.

Village Elementary School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium lights with new high efficient florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Farms Intermediate School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Ore Creek Middle School:
• Replaced all of the site lights with new high efficiency LED heads. • Replaced all of the gymnasium and auxiliary gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Hartland High School:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium and auxiliary gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

Educational Support Service Center:
• Replaced all of the site lights utilizing the existing light poles with new high efficiency LED heads.
• Replaced all of the gymnasium and auxiliary gymnasium lights with new high efficiency florescent T-4, T-5 fixtures, which will provide “instant on” capability. The design includes motion sensors that will turn the lights on and off automatically without switches.

51 Building:
Work started last month on the 51 building with the replacement of the existing counter tops and sinks. Lighting motion sensors have been installed in each of the classrooms as well as the commons area in order to conserve energy. The major focus of the project is to replace the existing roof top heating unit with a new more efficient unit - not only for heating but cooling as well. Later in June site work will begin that involves restoration of the hard surface play area as well as much needed drainage control.


2011 Summer Projects

District wide Site Work:

• Creekside Elementary School: Parking lot crack repairs, sealant, restriping and miscellaneous sidewalk repairs.
• Lakes Elementary School: Expansion of the existing parking lot from 15 parking spaces to 51 spaces. A separate entrance and exit for cars only will be created to provide for a safer parent drop off area.
• Farms Intermediate School: A separate entrance is being created just north of the boulevard bus entrance for parent drop off as well as access to the Farms parking lot. This will also separate cars from busses and make for a safer drop area for the students. (2006 Bond Project)
• Round Elementary School: Parking lot expansion to the existing south lot will add an additional 39 parking spaces. Site grading will also take place to help better define the existing drainage swale and improve and control the water draining from the south. Miscellaneous sidewalk repairs will also be done.
• Village Elementary School: An extension of the existing Epley Parking sidewalk toward the school. This will provide safer access to the school and around the north parking lot. The hard surface play area will be removed and replaced as well as some sidewalk repairs.
• Ore Creek Middle School: The staff and visitor parking lot will be removed and replaced. No change in the lot configuration is anticipated.
• Educational Support Service Center: The upper tennis courts are going to be removed and replaced. The lower tennis courts are scheduled to be removed and replaced with four new pickle ball courts. The existing storage building located west of the football field will be removed and replaced with a new storage building of a like size.

Building Renovation:

Farms Intermediate School:

Will undergo a complete mechanical system replacement that will include the following:
• New high efficiency boilers (2)
• New high efficiency heat pumps used for both heating & cooling (66)
• Replace the existing ceiling hung heating units with new roof top units capable of heating & cooling (2)
• New makeup air units (3) that will service the boys & girls locker rooms and the kitchen
• New heat piping throughout the building
• New base board heaters & cabinet unit heaters (13)
• New main circulation pumps (2)

Here are a few more items that will be included in the Farms renovation:
• The existing bare concrete floors in the art room areas will have a new vinyl tile floor installed along with wall paint
• Acoustical wall tiles will be installed in the cafeteria to reduce the sound reverberation
• Many of the existing interior doors will be replaced
• The exterior doors & frames at the main entrance, vestibule & the gymnasium emergency exits are scheduled to be replaced
• Partial exterior brick restoration around the building

Lakes Elementary School:

Will undergo a complete mechanical system replacement that will include the following:
• New high efficiency boilers (2)
• New high efficiency heat pumps used for both heating & cooling (38) • New makeup air units servicing the kitchen(1)
• New heat piping throughout the building
• New baseboard heaters & cabinet unit heaters (13)
• New main circulation pumps (2)

Here are a few more items that will be included in the Lakes renovation:
• Replace the existing boys and girls toilet room toilet partitions
• Replace the existing student coat hooks with new lockers
• Partial exterior brick restoration around the building
• New ceiling and lighting in the music room
• Partial exterior window replacement
• Partial interior door replacement
• Replace classroom sinks and countertops not previously done


Fall 2011 - Bond Completion

Round Elementary School:
• Create Sallyport entry
• Replace toilet room partitions, trim & faucets
• Replace gymnasium flooring
• Partial exterior door & frame replacement
• Install ceiling over duct work in office

Village Elementary School:
• Install additional corridor lockers
• Replace ceiling tile in classrooms & corridors • Install new exhaust fans in staff toilet rooms
• Reconstruct Epley Park toilet facilities

Ore Creek Middle School:
• Partial interior door replacement
• Replace ceiling tile in corridors & some classrooms
• Replace corridor carpet

Hartland High School:
• Replace cross corridor door
• Resurface both indoor & outdoor running tracks
• A/C in Health classrooms
• Replace pool equipment
• Install dehumidification system in pool area
• Install Variable speed motors on equipment
• Upgrade TV studio
• Replace duct work in Varsity locker rooms

Educational Support Service Center:
• Replace old existing boiler
• Partial replacement of existing Roof Top Units

Technology:
• The remainder of the bond scope after the summer of 2012 projects will be computer replacement of both instructional and non-instructional computers district wide.